Container cleaner Reiniger Bin

Renault Midlum 270 dxi CONTAINER BIN WASHER TECME / MOWA Mülltonnenreiniger

Specialist Vehicle for Waste Bin Cleaning

Renault Midlum 270 dxi
First registration: 2012
Current mileage: 208,120 km
Manual transmission
8-speed manual gearbox
Manual air conditioning
One spare wheel with a new tyre for the rear axle included



Waste Bin Cleaning Equipment – TECME / MOWA
Model: TCI130

The body is entirely manufactured from acid-resistant stainless steel.

The water tank is divided into two sections:

6,000 litres of fresh water
6,000 litres of dirty water

The equipment is fitted with three high-pressure pumps.

Two large high-pressure pumps:
HPP Comet Type CL 49/200, flow rate: 49 l/min. 
Pressure: 200 bar

One small pump: Interpump for water pistols.

One of the two HPP pumps supplies two washing heads (robots) located inside the washing chamber. These washing heads clean the waste bins from the inside.

The second HPP pump supplies the nozzles on the lances inside the washing chamber. These nozzles clean the waste bins from the outside. The lances move back and forth.

The third high-pressure pump, manufactured by Interpump, supplies the cleaning gun at the rear of the vehicle with high-pressure water. The gun is used for manual cleaning.

In addition, a new high-pressure cleaning gun for manual cleaning of waste bins has been installed. The new cleaning gun allows convenient manual cleaning of waste bins as well as hard-to-reach areas of the equipment.

The water supplied to the pumps is filtered through water filters.

The equipment is also fitted with two heating units for heating the washing water.

Both heating units are diesel-powered.

A lifting device for lifting waste bins is installed at the rear of the equipment.

The grab arms can handle waste bins from 110 litres up to large 1,100-litre four-wheel containers.

Dirty water is extracted by a sludge pump driven by a hydraulic motor. When the dirty water level rises in the rear section of the equipment, the pump is automatically activated by a sensor.

The machine provides easy access to the control and operating components of the equipment. The side exterior panels in the rear section can be easily removed.

Work and Renovation Carried Out:

– Complete renovation of the equipment: thorough cleaning, manual sanding, masking, application of epoxy primer and painting of the entire equipment, including the roof, with polyurethane paint in RAL 9016
– Removal of various equipment components such as side panels, hydraulic cylinder covers, storage compartments, lights, etc.
– Cleaning of the removed components and separate painting using the same process
– Renovation of the frame and chassis: thorough cleaning, manual sanding, masking, epoxy priming and painting with dark grey polyurethane paint
– Thorough cleaning of the rear section of the equipment with a descaling agent to remove limescale
– Cleaning and refurbishment of the wheels, masking, epoxy priming and painting the wheels silver
– Reassembly of the equipment, removal of masking, installation of equipment components, doors and storage compartments, as well as installation of lights, etc.
– Removal, replacement and installation of new rear mudguards
– Engine oil and oil filter change
– Replacement of the engine air filter
– Replacement of the fuel filter element
– Oil change in all three HPP Comet and Interpump high-pressure pumps
– Inspection, removal and servicing of the pneumatic control unit, followed by reinstallation
– Elimination of faults and leaks in the pneumatic system
– Replacement of the oil nozzles for fuel atomisation in both heating units: Danfoss 2.25 – 60°, 2 pieces
– Inspection of the electrical system and wiring of the equipment, replacement of fuses and relays, and cleaning of electrical components with isopropyl alcohol
– Replacement of defective Schneider switches on the equipment
– Complete removal of the waste bin lifting device, inspection for cracks and repair by stainless steel welding
– Removal of the grab arms for 1,100-litre containers, sandblasting and subsequent hot-dip galvanising of the components, followed by reinstallation
– Replacement of the grab arm pins for 1,100-litre containers with stainless steel pins; custom adjustment and manufacture by a machinist
– Replacement of the springs of the grab arms for 1,100-litre containers
– Removal and manufacture of new hydraulic hoses for the lifting and locking system of the containers
– Replacement of various hydraulic components on the lifting device, including nipples, fittings, as well as copper and steel-rubber seals
– Removal of the two large hydraulic cylinders responsible for lifting the entire lifting device, and replacement of the seals
– Installation of new LED lighting on the equipment
– Inspection and repair of damaged solenoid coils controlling the working hydraulics
– Inspection and repair of the water connections
– Replacement of corroded water-carrying components such as elbows and high-pressure fittings
– Inspection of the correct operation of all proximity sensors of the machine
– Removal of the pump heads from the HPP Comet high-pressure pumps to inspect the ceramic pistons
– Replacement of two cracked ceramic pistons with new original HPP COMET parts
– Removal of the side hydraulic manifold, servicing and replacement of pressure seals, elimination of the leak and reinstallation
– Inspection of the rear control panels for operating the equipment, troubleshooting and repair, including replacement of damaged wiring
– Vinegar was added to the fresh-water section of the tank to remove limescale deposits from the tank walls
– Sealing of the washing chamber
– Removal of the fuel tank and inspection of the fuel sender and suction strainer for contamination or blockage – no blockage was found – followed by reinstallation of the tank
– Thorough cleaning of the driver’s cab, upholstery cleaning and detailed cleaning of the interior panels, including the areas underneath the floor covering
– Removal, inspection and cleaning of the fine water filters, followed by reinstallation
– Inspection and adjustment of the operating settings of the Tecme control unit in the driver’s cab. Commissioning of the second heating unit. Extension of the washing time for waste bins. Extension of the operating time of the heating units
– Polishing of the driver’s cab and touch-up of paint damage
– Painting of the front bumper
– Replacement of the lower driver’s-side step for access to the driver’s cab
– Application of Oralite film to the driver’s cab
– Inspection and repair of the lighting system
– Final inspection

A detailed functional test of all components and systems of the equipment has been carried out.